Question 67  CFFA, interest tax shield

Here are the Net Income (NI) and Cash Flow From Assets (CFFA) equations:

###NI=(Rev-COGS-FC-Depr-IntExp).(1-t_c)###

###CFFA=NI+Depr-CapEx - \varDelta NWC+IntExp###

What is the formula for calculating annual interest expense (IntExp) which is used in the equations above?

Select one of the following answers. Note that D is the value of debt which is constant through time, and ##r_D## is the cost of debt.



Question 360  CFFA

Find Ching-A-Lings Corporation's Cash Flow From Assets (CFFA), also known as Free Cash Flow to the Firm (FCFF), over the year ending 30th June 2013.

Ching-A-Lings Corp
Income Statement for
year ending 30th June 2013
  $m
Sales 100
COGS 20
Depreciation 20
Rent expense 11
Interest expense 19
Taxable Income 30
Taxes at 30% 9
Net income 21
 
Ching-A-Lings Corp
Balance Sheet
as at 30th June 2013 2012
  $m $m
Inventory 49 38
Trade debtors 14 2
Rent paid in advance 5 5
PPE 400 400
Total assets 468 445
 
Trade creditors 4 10
Bond liabilities 200 190
Contributed equity 145 145
Retained profits 119 100
Total L and OE 468 445
 

 

Note: All figures are given in millions of dollars ($m).

The cash flow from assets was:



Question 370  capital budgeting, NPV, interest tax shield, WACC, CFFA

Project Data
Project life 2 yrs
Initial investment in equipment $600k
Depreciation of equipment per year $250k
Expected sale price of equipment at end of project $200k
Revenue per job $12k
Variable cost per job $4k
Quantity of jobs per year 120
Fixed costs per year, paid at the end of each year $100k
Interest expense in first year (at t=1) $16.091k
Interest expense in second year (at t=2) $9.711k
Tax rate 30%
Government treasury bond yield 5%
Bank loan debt yield 6%
Levered cost of equity 12.5%
Market portfolio return 10%
Beta of assets 1.24
Beta of levered equity 1.5
Firm's and project's debt-to-equity ratio 25%
 

Notes

  1. The project will require an immediate purchase of $50k of inventory, which will all be sold at cost when the project ends. Current liabilities are negligible so they can be ignored.

Assumptions

  • The debt-to-equity ratio will be kept constant throughout the life of the project. The amount of interest expense at the end of each period has been correctly calculated to maintain this constant debt-to-equity ratio. Note that interest expense is different in each year.
  • Thousands are represented by 'k' (kilo).
  • All cash flows occur at the start or end of the year as appropriate, not in the middle or throughout the year.
  • All rates and cash flows are nominal. The inflation rate is 2% pa.
  • All rates are given as effective annual rates.
  • The 50% capital gains tax discount is not available since the project is undertaken by a firm, not an individual.

What is the net present value (NPV) of the project?



Question 564  covariance

What is the covariance of a variable X with a constant C?

The cov(X, C) or ##\sigma_{X,C}## equals:



Question 613  debt terminology

You own a debt asset. Are you a or a ?


Question 694  utility

Which of the below statements about utility is NOT generally accepted by economists? Most people are thought to:



Question 753  NPV, perpetuity, DDM

The following cash flows are expected:

  • A perpetuity of yearly payments of $30, with the first payment in 5 years (first payment at t=5, which continues every year after that forever).
  • One payment of $100 in 6 years and 3 months (t=6.25).

What is the NPV of the cash flows if the discount rate is 10% given as an effective annual rate?



Question 867  limited liability, business structure

Which one of the following businesses is likely to be a public company in Australia, judging by its name?



Question 919  duration, bond convexity

Which of the following statements about bond convexity is NOT correct?



Question 930  arbitrage table, future, no explanation

A non-dividend paying stock has a current price of $20.

The risk free rate is 5% pa given as a continuously compounded rate.

A 2 year futures contract on the stock has a futures price of $24.

You suspect that the futures contract is mis-priced and would like to conduct a risk-free arbitrage that requires zero capital. Which of the following steps about arbitraging the situation is NOT correct?