Fight Finance

Courses  Tags  Random  All  Recent  Scores

Question 66  CAPM, SML

Government bonds currently have a return of 5% pa. A stock has an expected return of 6% pa and the market return is 7% pa. What is the beta of the stock?



Question 161  DDM

A share just paid its semi-annual dividend of $10. The dividend is expected to grow at 2% every 6 months forever. This 2% growth rate is an effective 6 month rate. Therefore the next dividend will be $10.20 in six months. The required return of the stock 10% pa, given as an effective annual rate.

What is the price of the share now?



Question 203  fully amortising loan, APR

You just signed up for a 30 year fully amortising mortgage loan with monthly payments of $1,500 per month. The interest rate is 9% pa which is not expected to change.

How much did you borrow? After 10 years, how much will be owing on the mortgage? The interest rate is still 9% and is not expected to change.



Question 228  DDM, NPV, risk, market efficiency

A very low-risk stock just paid its semi-annual dividend of $0.14, as it has for the last 5 years. You conservatively estimate that from now on the dividend will fall at a rate of 1% every 6 months.

If the stock currently sells for $3 per share, what must be its required total return as an effective annual rate?

If risk free government bonds are trading at a yield of 4% pa, given as an effective annual rate, would you consider buying or selling the stock?

The stock's required total return is:



Question 345  capital budgeting, break even, NPV

Project Data
Project life 10 yrs
Initial investment in factory $10m
Depreciation of factory per year $1m
Expected scrap value of factory at end of project $0
Sale price per unit $10
Variable cost per unit $6
Fixed costs per year, paid at the end of each year $2m
Interest expense per year 0
Tax rate 30%
Cost of capital per annum 10%
 

Notes

  1. The firm's current liabilities are forecast to stay at $0.5m. The firm's current assets (mostly inventory) is currently $1m, but is forecast to grow by $0.1m at the end of each year due to the project.
    At the end of the project, the current assets accumulated due to the project can be sold for the same price that they were bought.
  2. A marketing survey was used to forecast sales. It cost $1.4m which was just paid. The cost has been capitalised by the accountants and is tax-deductible over the life of the project, regardless of whether the project goes ahead or not. This amortisation expense is not included in the depreciation expense listed in the table above.

Assumptions

  • All cash flows occur at the start or end of the year as appropriate, not in the middle or throughout the year.
  • All rates and cash flows are real. The inflation rate is 3% pa.
  • All rates are given as effective annual rates.

Find the break even unit production (Q) per year to achieve a zero Net Income (NI) and Net Present Value (NPV), respectively. The answers below are listed in the same order.



Question 369  interest tax shield, CFFA

One formula for calculating a levered firm's free cash flow (FFCF, or CFFA) is to use earnings before interest and tax (EBIT).

###\begin{aligned} FFCF &= (EBIT)(1-t_c) + Depr - CapEx -\Delta NWC + IntExp.t_c \\ &= (Rev - COGS - Depr - FC)(1-t_c) + Depr - CapEx -\Delta NWC + IntExp.t_c \\ \end{aligned} \\###
Does this annual FFCF or the annual interest tax shield?


Question 370  capital budgeting, NPV, interest tax shield, WACC, CFFA

Project Data
Project life 2 yrs
Initial investment in equipment $600k
Depreciation of equipment per year $250k
Expected sale price of equipment at end of project $200k
Revenue per job $12k
Variable cost per job $4k
Quantity of jobs per year 120
Fixed costs per year, paid at the end of each year $100k
Interest expense in first year (at t=1) $16.091k
Interest expense in second year (at t=2) $9.711k
Tax rate 30%
Government treasury bond yield 5%
Bank loan debt yield 6%
Levered cost of equity 12.5%
Market portfolio return 10%
Beta of assets 1.24
Beta of levered equity 1.5
Firm's and project's debt-to-equity ratio 25%
 

Notes

  1. The project will require an immediate purchase of $50k of inventory, which will all be sold at cost when the project ends. Current liabilities are negligible so they can be ignored.

Assumptions

  • The debt-to-equity ratio will be kept constant throughout the life of the project. The amount of interest expense at the end of each period has been correctly calculated to maintain this constant debt-to-equity ratio. Note that interest expense is different in each year.
  • Thousands are represented by 'k' (kilo).
  • All cash flows occur at the start or end of the year as appropriate, not in the middle or throughout the year.
  • All rates and cash flows are nominal. The inflation rate is 2% pa.
  • All rates are given as effective annual rates.
  • The 50% capital gains tax discount is not available since the project is undertaken by a firm, not an individual.

What is the net present value (NPV) of the project?



Question 543  price gains and returns over time, IRR, NPV, income and capital returns, effective return

For an asset price to triple every 5 years, what must be the expected future capital return, given as an effective annual rate?



Question 601  foreign exchange rate, American and European terms

Australians usually quote the Australian dollar in USD per 1 AUD. For example, in October 2015 the Australian dollar was quoted as 0.72 USD per AUD. Is this an or terms quote?


Question 740  real and nominal returns and cash flows, DDM, inflation

Taking inflation into account when using the DDM can be hard. Which of the following formulas will NOT give a company's current stock price ##(P_0)##? Assume that the annual dividend was just paid ##(C_0)##, and the next dividend will be paid in one year ##(C_1)##.